TM 5-3805-264-13&P
0017
Table 1. Operator Preventive Maintenance Checks and Services (PMCS) - Continued.
ITEM TO BE
EQUIPMENT
ITEM
CHECKED OR
NOT READY/
NO.
INTERVAL
SERVICED
PROCEDURE
AVAILABLE IF:
2. Inspect hydraulic cylinder (Figure 14, Item 2),
Damage to components
hydraulic reservoir (Figure 14, Item 1), and hydraulic
or Class III hydraulic fluid
lines and fittings for loose mounting, leaks, or
leaks are evident.
damaged components.
3. Remove body props and lower dump body
Figure 14. Hydraulic System.
WARNING
18
Monthly
Body Props
NEVER work under a raised dump body
unless it is secured in the raised position
with body props and dump body is EMPTY.
Failure to comply may result in personnel
injury or death.
1. Raise dump body and support on body props
Body props are damaged
or cannot be installed to
safely support dump
body.
2. Apply grease to grease fitting (Figure 15, Item 2) on
each body prop (Figure 15, Item 1).
03/15/2011Rel(1.10)root(pmcswp)wpno(I1000226413)