TM 5-3805-264-14&P
4-71.
HYDRAULIC CONTROL LEVER CABLE REPLACEMENT (Cont).
25.
Remove nut (49) and cable bracket (46).
26.
Count number of threads from end of cable (36) to nut (50).
27.
Remove nut (50).
1.
Install nut (50) onto cable (36) same number of threads as removal.
2.
Slide cable bracket (46) onto cable (36) and install nut (49).
3.
Position cable bracket (46) onto hydraulic pump actuator (48) and install clevis pin (45) and new cotter pin
(47).
4.
Slide spacer (44), screw bonnet (39) and slide flange clamp (43) over cable bracket (46).
5.
Install two screws (40), flatwashers (42) and new lockwashers (41) to flange clamp (43).
6.
Slide jam nut (38) onto cable (36).
7.
Tighten jam nut (38) against flange clamp (43).
8.
Install transmission tunnel access cover (TM 9-2320-363-20).
9.
Install four screws (37) securing shift tower (1)
to cab floor.
4-128